Sponsor Details
| |
|
COMMUNITY COGNITIVE MENTOR
THERAPY BUS |
|
YEARLY BUDGET
|
2007 - |
2008 |
| |
Yearly Cost |
|
Weekly Cost |
Monthly Cost |
|
PERSONNEL |
|
Hourly Rate / 30HRS. |
|
|
|
Program Director |
$39,950.00 |
$25.61 |
$768.27 |
$3,329.17 |
|
FICA @ 7.65% |
$3,056.18 |
|
$58.77 |
$254.68 |
|
Full-time Administrative Assistant |
$29,950.00 |
$19.20 |
$575.96 |
$2,495.83 |
|
FICA @ 7.65% |
$2,291.18 |
|
$44.06 |
$190.93 |
|
Psychotherapist |
$65,000.00 |
$41.67 |
$1,250.00 |
$5,416.67 |
|
FICA @ 7.65% |
$4,972.50 |
|
$95.63 |
$414.38 |
| |
|
Hourly Rate / 40HRS. |
|
|
|
Personal Development Associate # 1 Full-time |
$20,000.00 |
$9.62 |
$384.62 |
$1,666.67 |
|
FICA @ 7.65% |
$1,530.00 |
|
$29.42 |
$127.50 |
|
Educational Development Associate # 2 Full-time |
$20,000.00 |
$9.62 |
$384.62 |
$1,666.67 |
|
FICA @ 7.65% |
$1,530.00 |
|
$29.42 |
$127.50 |
|
Bus Driver - Full time |
$35,000.00 |
$16.83 |
$673.08 |
$2,916.67 |
|
FICA @ 7.65% |
$2,677.50 |
|
$51.49 |
$223.13 |
| |
|
Hourly Rate / 15HRS. |
|
|
|
Economic Mentor # 1Part-time |
$5,295.00 |
$6.79 |
$101.83 |
$441.25 |
|
FICA @ 7.65% |
$405.07 |
|
$7.79 |
$33.76 |
|
Educational Mentor # 2 Part-time |
$5,295.00 |
$6.79 |
$101.83 |
$441.25 |
|
FICA @ 7.65% |
$405.07 |
|
$7.79 |
$33.76 |
|
Educational Mentor # 3 Part-time |
$5,295.00 |
$6.79 |
$101.83 |
$441.25 |
|
FICA @ 7.65% |
$405.07 |
|
$7.79 |
$33.76 |
| |
|
|
|
|
|
Health Insurance / All Employees |
$81,360.00 |
$565 fam. plan / 12 emp. |
|
$6,780.00 |
| |
|
|
|
|
|
EQUIPMENT COSTS |
|
|
|
|
|
Transmission - |
$1,200.00 |
|
ONE TIME COST |
|
|
Master Brake Cylinder - |
$550.00 |
|
ONE TIME COST |
|
|
Wiring |
$500.00 |
|
ONE TIME COST |
|
|
Towing |
$500.00 |
|
ONE TIME COST |
|
|
Air Conditioner |
$900.00 |
|
ONE TIME COST |
|
|
Interior Rehabilitation |
$1,800.00 |
|
ONE TIME COST |
|
|
Interior Security Door & Partition |
$1,500.00 |
|
ONE TIME COST |
|
|
Furnishings |
$5,000.00 |
|
ONE TIME COST |
|
|
Exterior Body Work |
$2,500.00 |
|
ONE TIME COST |
|
|
Painting |
$2,000.00 |
|
ONE TIME COST |
|
| |
|
|
|
|
|
COGNITIVE DELIVERY EQUIPMENT (reqd.) |
|
|
|
|
|
DVD/CD Player |
$350.00 |
|
ONE TIME COST |
|
|
Digital Cameras (2) |
$5,000.00 |
|
ONE TIME COST |
|
|
Laptop Computer |
$1,940.00 |
|
ONE TIME COST |
|
|
Production Computer G5 |
$6,850.00 |
|
ONE TIME COST |
|
|
DVD Production Equipment |
$12,450.00 |
|
ONE TIME COST |
|
|
TELEVISION |
$895.00 |
|
ONE TIME COST |
|
|
SATELLITE TV/ INTERNET |
$1,800.00 |
|
$34.62 |
$150.00 |
| |
|
|
|
|
|
OFFICE EQUIPMENT |
|
Quantity |
|
|
|
Brochures @ $5 for 100 |
$250.00 |
5,000 |
|
|
|
DVD / CD Media |
$6,250.00 |
5,000 |
|
|
|
Postage |
$13,500.00 |
2,500 |
|
$1,125.00 |
|
Business Cards - Director |
$150.00 |
1,000 |
|
|
|
Letterhead / Envelopes |
$150.00 |
1,000 |
|
|
|
Miscellaneous Office Supplies |
$450.00 |
|
|
|
|
Program Recruitment DVD/CD |
$6,250.00 |
5,000 |
|
|
|
File cabinet, 2 desks, 2 chairs |
$1,950.00 |
|
|
|
|
Literature Packs / Folders |
$6,345.00 |
|
$122.02 |
$528.75 |
|
Business Telephone / Intercom System |
$5,000.00 |
|
|
|
|
Cleaning / Maintenance Equipment |
$5,000.00 |
Hardware & Supplies |
|
|
|
Lecture / Public Address System |
$1,200.00 |
|
|
|
|
Training Room Furnishings |
$4,500.00 |
|
|
|
|
Overhead Projection System |
$4,500.00 |
|
|
|
|
Facsimile |
$250.00 |
|
|
|
|
Color Laser Printer |
$1,450.00 |
|
|
|
|
Inkjet Printer Epson 2200 |
$845.00 |
|
|
|
|
Office Desktop Computers (2) |
$3,450.00 |
|
|
|
|
DVD/CD Printer |
$3,450.00 |
|
|
|
| |
|
|
|
|
|
BUS EXPENSES |
|
|
|
|
|
GASOLINE @ $80/week |
$8,320.00 |
|
$160.00 |
$693.33 |
|
REPAIRS |
$2,500.00 |
|
$48.08 |
$208.33 |
|
TOLLS & ROAD MISC. |
$5,200.00 |
|
$100.00 |
$433.33 |
|
Insurance (per year) |
$2,500.00 |
|
$48.08 |
$208.33 |
|
DMV Fees (per year) |
$250.00 |
|
$4.81 |
$20.83 |
| |
|
|
|
|
|
ON THE ROAD OPERATION |
|
|
|
|
|
LITERATURE PACKETS |
$12,000.00 |
|
$230.77 |
$1,000.00 |
|
FOOD 3 MEALS/DAYx2 |
$21,900.00 |
|
$421.15 |
$1,825.00 |
| |
Yearly Cost |
|
Weekly Cost |
Monthly Cost |
|
Total Costs |
$487,762.55 |
|
$9,380.05 |
$40,646.88 |
|